Custom J1939 Harness From Drawing to PPAP: Why Programs Slip, and the 6-Stage Workflow That Prevents It

Custom J1939 harness with 9-pin Deutsch connector, engineering drawing and crimp cross-section on a test bench

Reviewed November 2026. Applies to J1939-11 at 250 kbit/s and J1939-14 at 500 kbit/s.

A test-bench builder sent us a drawing revision C in March: a 4.2 m J1939 backbone, 9-pin Deutsch diagnostic tee, 18 AWG power and ground, shielded twisted pair for CAN, twenty-two nodes, and a PPAP date eleven weeks out.

The drawing was clean. Title block correct, connector callouts correct, wire list complete, tolerance block filled in. It was also electrically incomplete in three places nobody would notice until the harness was on a running engine.

At 500 kbit/s with the alternator loaded, the bus threw error frames roughly every ninety seconds. The shield drain was terminated with a 60 mm pigtail to pin E. The CAN pair had no lay length called out, and the production sample had come in at 38 mm. The pair then ran parallel to a 24 V accessory feed for 1.1 m with no separator.

Every part met the drawing. The program was still going to miss PPAP, because PPAP is not where harness programs fail. They fail in week one, at drawing review, and nobody finds out until the PSW is due.

What follows is that gap, walked stage by stage in the order a custom J1939 harness actually moves through a factory, with the evidence we hand over at each gate.

What “drawing to PPAP” actually covers

Every PPAP argument we have sat through in ten years came down to one question: does this package describe a process, or does it describe five good parts?

The eighteen-element checklist does not answer that question. It was written for a world where the parts already exist and the argument is about paperwork. A run-at-rate record with a rework log answers it, because a process that produces defects and corrects them in front of you is a process you can predict.

Everything below follows from that distinction. Each gate exists because a different person will eventually read the file: a customer SQA engineer, an auditor, a line operator eight months from now. None of them were in the room when the part was built, and the paperwork has to hold up without you standing next to it.

The six stages at a glance

StageWhat happensGate outputTypical calendar
1Drawing intake and requirement decompositionSigned review record, open-issue list1–2 weeks
2Electrical and thermal dimensioningWire schedule, voltage-drop and derating calc3–5 days, parallel with 1
3Prototype build and first articleFAI report, master samples
2–3 weeks
4
Design and process validation
DV/PV report with in-situ data
6–10 weeks
5Process validation and control planPFMEA, control plan, MSA, Cpk study3–4 weeks, overlaps 4
6PPAP submission and PSWLevel 3 package, signed PSW2–3 weeks

Budget twelve to eighteen weeks for a new design, end to end. A variant on an already validated platform, where the connector family, terminal system and crimp process are proven, can run six to eight. The variable is almost never assembly speed. It is how much of stage 4 has to be repeated, and that number is set by how well stage 1 was done.

Stage 1 — Drawing intake and requirement decomposition

Before we quote, we read the drawing three times: once as a mechanical part, once as an electrical circuit, once as a test specimen. Most custom J1939 harness drawings describe the first two well and the third badly.

The intake package we ask for:

  • Drawing in PDF and, where possible, native CAD or the original wire-list spreadsheet
  • Connector list with housing, terminal, seal, cavity plug and retainer part numbers
  • Node count, baud rate, trunk length, stub lengths
  • Routing environment: engine-mounted, chassis, cab or test cell; ambient at the hottest point; static or flexing
  • Mating half part numbers and keying
  • End-of-line test definition, PPAP level, annual volume, service life
  • Full change history, not just the current revision

Change history is the page customers skim and we read first. A revision that silently moved a terminal from tin-over-nickel to bare tin will fail salt spray in month four, and the current drawing will not tell you it happened.

The twelve-point drawing review we run on every J1939 harness

#Check
Why it bites
1Connector view convention: wire side or mating faceMirrored 9-pin pinouts are the most common single error we see
2Cavity lettering versus numberingDeutsch uses letters; some OEM housings number cavities
3Terminal plating calloutTin over nickel versus bare tin changes corrosion life by years
4Seal and cavity plug calloutsA missing plug quietly voids the IP67 claim
5CAN pair lay length20 ± 5 mm at 500 kbit/s, around 25 mm at 250 kbit/s
6Shield termination method
360° backshell clamp versus drain pigtail
7Shield grounding pointOne end, named, with the reason written down
8Splice location and methodUltrasonic versus crimp splice, and which zone it may sit in
9Bend radius and strain relief at the connectorThe failure usually starts 40 mm behind the backshell
10Wire gauge against load, length and ground returnThe return path is the one that gets forgotten
11Temperature rating of jacket, terminal and seal versus ambientA 105 °C PVC jacket on a 125 °C manifold is a scheduled return
12Label and traceability locationDate code and serial must survive the routing, not just the bench

On the revision C drawing, this review took four hours and produced three findings: the pigtail, the missing lay length, and the parallel run. The customer accepted all three.

What a late discovery actually costs

Delay is easier to argue about once it is written down. These are the slips we have recorded on J1939 programs, sorted by the gate where the drawing defect finally surfaced.

Where the defect surfacesDelay to PSWRework
Drawing review, week 1
none

A drawing note
Prototype and FAI, week 41–2 weeksRe-terminate, reseal, new sample lot
DV/PV, week 104–6 weeksNew tooling insert, repeat the affected test block, reissue PPAP
Run-at-rate, week 156–8 weeksApplicator change, full revalidation, PSW re-signature
After PSW, in production10–16 weeksContainment, sort, ECN, customer notification, possible field campaign

The same three-line finding that costs a phone call in week one costs a program six weeks in week ten. That is the whole case for stage 1, and it is why we run the review before quoting rather than after winning the order.

Stage 2 — Electrical and thermal dimensioning

J1939 is a physical layer problem wearing a protocol costume. Most communication faults we investigate on a J1939 cable assembly turn out to be voltage-drop, shield or impedance problems that the network reports as node failures, even though the SAE J1939 physical-layer requirements are explicit about all three.

Wire gauge, resistance and what actually fits

AWGResistance at 20 °CTypical J1939 rolePractical note
2252.9 Ω/kmShort signal stubs, sensor returnsDrop becomes significant past about 1 m under load
20
33.3 Ω/km
CAN-H / CAN-L pair, DTM terminalsThe default for the differential pair
1820.9 Ω/kmPower and ground, DT terminalsRoughly 4–5 A continuous over 3 m
1613.2 Ω/kmMain battery feed, DTP terminalsRoughly 7–8 A over 5 m
148.28 Ω/kmLong runs, high-current devices12 A class, watch bend radius

The calculation that matters is the loop, not the run. A sensor 7 m away has 14 m of conductor in its circuit, and the return path carries exactly the same current as the feed. We work through that arithmetic, and what it does to ground separation on a bench setup, in test-bench cable AWG, loop resistance and ground separation.

A worked example: the 5 V rail that drifted out of tolerance

A recent test-cell program had a 5 V reference rail feeding four pressure sensors and a position encoder, 0.85 A total, on 18 AWG over 7 m one way.

Conductor resistance was 0.29 Ω, so 0.25 V was lost in copper. Two sealed splices and a connector pair measured 0.18 Ω on a four-wire check, adding 0.15 V. Total drop 0.40 V, which is eight percent of a 5 V reference against a sensor accuracy specification of plus or minus two percent.

At 105 °C conductor temperature, copper resistance rises by about a third. The drop reached 0.48 V, just under ten percent. Nothing failed outright. The readings drifted out of tolerance at high load, the ECM logged implausible-data faults, and the first two harnesses sent back to us tested perfect on the bench.

Rebuilt in 16 AWG with one splice moved back to the backbone, the cold drop came to 0.23 V and the hot drop to 0.29 V. The fault codes stopped and stayed stopped through a 72-hour soak.

Shield strategy, stated plainly

Terminate the shield 360° at the backshell, at one end, and write down which end. A 60 mm drain pigtail adds series inductance at exactly the frequencies you are trying to keep out of the pair, and it turns the shield into a stub antenna.

Both-end grounding is legitimate on a bonded chassis where the potential difference is small, and it is a ground loop everywhere else. If a customer specifies both ends, we ask for the bonding resistance between the two points. Where nobody has measured it, we recommend single-point grounding at the ECM end and a 4.7 nF class capacitor at the far end for RF bleed.

Bend radius and routing

Six times the outer diameter for static routing, ten times for anything that flexes. On a 9 mm jacketed backbone that is 54 mm static and 90 mm dynamic.

Harnesses that fail at eighteen months usually broke this rule in the first 100 mm behind the connector, where the bend is tightest and the strain relief is doing nothing.

If you are at stage 1 or 2 with a drawing in hand and nobody has run these numbers, that is the moment to talk to an engineer rather than a sales inbox: WhatsApp the engineering desk or use the contact page. Send the drawing and the environment, and you will get a review back.

Stage 3 — Prototype build and first article

We build five prototypes: three to the customer, two retained as master samples, signed, dated, and stored with the PPAP file.

The first article inspection covers more than dimensions:

  • Housing, terminal, seal and retainer part numbers verified against the drawing, not against the pick list
  • Crimp height and width on every terminal, measured with a calibrated micrometer, not inferred from the applicator setting
  • Pull force per terminal family to SAE/USCAR-21; a 20 AWG terminal specified at 90 N minimum typically measures 118 N mean and 96 N minimum in a stable process
  • Cross-section on one terminal per crimp setup, void area under ten percent, no strand clipping, no insulation in the crimp barrel
  • Continuity and pinout, cavity by cavity, against the wire list
  • Insulation resistance at 500 V DC, 100 MΩ minimum
  • Dielectric withstand, 1,000 V AC for one second between adjacent circuits

The three prototype mistakes we see most

Hand-crimped terminals on a sample that will later be compared to production parts. Interface seals damaged by inserting the wrong tool. Splices placed where the drawing had space but the routing does not.

Any of these makes the prototype a poor reference for the process, and the master sample becomes a liability instead of an asset. A master sample that was built by a technician in twenty minutes is not a standard, it is a souvenir.

Stage 4 — Design and process validation

Stage 4 is the longest, and the stage customers consistently underfund, because it is the only one where the harness is treated as a component that must survive something rather than a drawing that has been assembled.

What we run, and what we refuse to run

A ten-row table of standard tests proves we own the standard document. It does not prove we have run anything. Four tests carry most of the risk on a custom J1939 harness, and the decision about what to skip is where engineering judgment shows up.

TestReferenceCondition we runPass criterion
Thermal cyclingISO 16750-4−40 to +125 °C, 100 cycles, 30 min dwellResistance shift under 10%, no interrupt over 100 µs
Random vibrationISO 16750-310–2,000 Hz, 8 h per axis, 3 axesNo discontinuity, no housing damage
Salt spray
ISO 9227 NSS
96 h cab, 480 h chassis and wheel-spray zonesNo base-metal corrosion
IngressIEC 60529 / ISO 20653IP67 mated, IP6K9K in engine bayNo ingress
Chemical resistanceISO 16750-5Fuel, oil, coolant, brake fluid, ureaSwelling under 10%, no cracking
Flex and matingInternal, connector spec100,000 cycles at 10× OD; 25–100 mating cyclesContinuity held, insertion force within 20%

We do not run 480-hour salt spray on cab harnesses. It adds six weeks and answers a question the routing already answered. We do run it on anything that sees wheel spray, and the rule came out of a coastal-fleet salt spray programme where the terminals failed long before the housings did. We also measure plating thickness by XRF before the test starts rather than after, because a 3 µm tin layer over brass with no nickel underplate fails at 72 hours and the report will blame the connector.

Two habits that separate evidence from a report

Monitor in situ. A harness that is unplugged during vibration and inspected afterwards proves almost nothing. We log resistance continuously and count every interruption longer than 100 µs.

Separate the connector from the terminal in the finding. On one program a 96-hour salt spray sample showed red rust at 72 hours. The housing was intact. The terminal was 3 µm tin directly over brass, no nickel underplate. We moved to tin over 1.5 µm nickel, repeated the test, and the 480-hour chassis sample passed with no base-metal corrosion. Had the report said only “connector failed,” the corrective action would have been to change a housing that was never the problem.

Stage 5 — Process validation, PFMEA and the control plan

A validated design built by an uncontrolled process becomes a warranty claim with a nice binder attached.

The PFMEA for a J1939 harness is short. The failure modes that matter are crimp height drift, the wrong terminal in a cavity that accepts two part numbers, a shield clamp not fully seated, a seal rolled during insertion, a splice in the wrong zone, and a label applied over a jacket seam.

Each one gets a detection method a person can perform at rate. “Operator awareness” is not a detection method; it is a hope with a signature under it.

Capability, not just conformance

Initial process studies run on crimp height and pull force. We hold Cpk at 1.67 or better for initial submission and 1.33 or better in ongoing production. Measurement systems get checked first, because a crimp height micrometer study above ten percent GR&R will make a good process look unstable and a bad one look fine. The reason we chase crimp height rather than pull force alone is simple: pull force passes and the part fails anyway, which is the argument in crimp height versus compression ratio.

One program came in at Cpk 0.98 on crimp height across a 300-piece study run over three shifts. The applicator was set once per shift and never monitored between setups. The fix was a crimp height check every 500 pieces with the result written into the lot record, plus applicator preventive maintenance on a fixed interval. Six weeks later, the same terminal on the same applicator ran at 1.72.

Poka-yoke that costs almost nothing

Color-coded seals per circuit function. Keyed housings that physically refuse the wrong mating half. Length-specific build fixtures, so a 4.2 m backbone cannot be built on a 3.8 m board. Cavity plugs staged in the kit rather than loose in a bin.

Stage 6 — PPAP submission and PSW

Level 3 is the default for most OEM harness programs, and it is where the drawing to PPAP sequence ends: full package to the customer, sample parts retained at the supplier. Level 4 adds customer-defined requirements. Level 5 is an on-site review of the package and the process together.

The six PPAP elements where harness packages usually fail

The eighteen-element list is public and every supplier reproduces it. What matters is what gets attached to each element, and that part is not in the standard. Our own element-by-element structure is described in PPAP Level 3 documentation for OBD cable assemblies; the table below is the short version.

PPAP elementWhat we attach that most packages omit
PFMEAThe shield-clamp seating failure mode, with the detection method and the fixture photograph
MSAGR&R on crimp height taken across three shifts, not one
Material and performanceXRF plating thickness measured before salt spray, not after
Initial process studiesCrimp height Cpk by applicator, not by part number
Master sampleChain of custody from build date to PPAP date, signed by the inspector
PSWRun-at-rate defect log, including the pieces that were reworked

If the PPAP question on your program is specifically about ripple coupling test content rather than package structure, that subject is covered separately in our ripple-to-bus coupling test guide for J1939 alternators.

Run-at-rate and the signature

Run-at-rate closes the loop: a production-rate run, typically 300 pieces, with 100% end-of-line test, first and last piece FAI, and a defect count that reaches zero on safety-critical characteristics. The PSW is signed after that run.

A signed PSW with no run-at-rate record behind it is decoration. Ask for the record.

The real calendar, from a program that shipped

The six-stage table above is the plan. This is what a 17-week J1939 harness program actually looked like, including the week it went sideways.

WeekWhat happenedGate
0Drawing rev C received; four-hour review returns three findingsReview record signed
1Customer accepts pigtail and lay length changes; rev D issued; two weeks lost waiting on connector samplesRev D frozen
3Wire schedule and voltage-drop calc issued; 16 AWG adopted on the 5 V railCalculation approved
4–6Five prototypes built, FAI on 42 crimps, two master samples retainedFAI signed
7First vibration run aborts at 4 h on axis 2: one terminal not fully latchedContainment, re-terminate, PFMEA updated
8–14
DV repeated: 100 thermal cycles, three-axis vibration, 480 h salt spray on the chassis sample
DV report issued
15Cpk study, 300 pieces over three shiftsCpk 1.71
16Run-at-rate, 300 pieces, two defects, both reworked and loggedRun-at-rate record
17PPAP Level 3 submitted; PSW signedPSW

Where custom J1939 programs actually break

Eight failure signatures and what to check first

Symptom on the bench or in the field
Likely root cause
What to check firstCorrective action
Bus goes silent after a 40-minute hot soakShield termination, seal compression set, lay length driftShield method, pair lay, stub length360° clamp, single-point ground, 20 ± 5 mm lay
Dropout under vibration onlyTerminal crimped on insulation, or oversized sealCrimp cross-section, pull forceRe-terminate, correct seal, add strain relief
Corrosion at 72 h salt sprayMissing nickel underplate on a tin-plated terminalXRF plating thicknessChange plating stack, revalidate
Continuity passes at EOL, fails in serviceHipot and continuity only, no loaded resistance testEOL test definitionAdd four-wire resistance under load
Housing cracks at the backshellBend radius violated, no strain reliefFirst 100 mm of routingReroute, add boot, specify 10× OD dynamic
Water in the connectorUnmated IP rating claimed, or missing cavity plugsMated versus unmated spec, plug calloutsCorrect the claim, add plugs, retest mated
Pinout wrong on 9-pin DeutschMirror view error between wire side and mating faceDrawing view conventionRedraw with an explicit view note
Resistance drifts upward over thermal cyclesCrimp relaxation, wrong terminal for the wire classCross-section after cyclingChange terminal series, recalibrate applicator

The first row is the one that generates the most service calls, and the electrical diagnosis behind it is long enough to deserve its own treatment. If the symptom is intermittent error frames rather than a dead bus, start with our J1939 harness audit for alternator ripple and common-mode noise.

What our end-of-line data says about where defects are born

Opinions about defect causes are cheap. Below is the distribution from 41,200 J1939 and diagnostic assemblies tested on our end-of-line stations last year, 1,180 defects in total, all caught before packing.

Where the 1,180 defects came from

RankFailure modeShare of defectsCaught by
1Terminal not fully seated or latched in cavity31%Pull-test fixture and visual gate
2Pinout error against the wire list
22%
100% continuity and pinout test
3Open circuit after crimp
17%

Four-wire resistance under load
4Seal rolled, cut or missing14%Visual gate plus IP sample
5Insulation resistance below limit9%500 V DC insulation test
6Other7%—

Look at the top two rows rather than the ranking. The largest category is not a crimp problem at all, it is a seating problem, which is why the seating fixture exists. And the second largest is a documentation problem, not a manufacturing one, which is why the wire list and the drawing revision are reconciled at the start of every build.

How to confirm the fix actually worked

“It passed” is not a result. These are the five conditions we require before a corrective action is closed:

Five conditions before a corrective action is closed

  1. Zero error frames over a 72-hour soak at the upper ambient, with the load that originally triggered the fault.
  2. No continuity interruption longer than 100 µs across 100 thermal cycles, logged in situ.
  3. Crimp height Cpk at 1.67 or better on the production applicator, measured across shifts.
  4. A salt spray sample that reaches full duration with no base-metal corrosion, with plating thickness verified by XRF before the test starts.
  5. A PPAP package where the drawing revision, the build date and the test date agree.

If any one of those five is missing, the fault is contained, not fixed.

Before you release the drawing to a supplier

Most supplier evaluations run in the wrong order: factory tour, sample bag, quotation. The tour shows the cleanest line, the sample bag shows the best parts, and neither tells you whether the process holds in month nine.

Two documents worth more than a factory tour

Two documents answer that faster than a visit. Ask for twelve records from the crimp terminal supplier, and ask what the harness supplier does about alternator ripple. If you want the short version before the visit, start with the qualification questions that separate a harness manufacturer from a reseller. The long versions are here:

What we can show you in our own plant

Our oldest J1939 assembly still in service was built in 2004 for a dynamometer cell in the north of England. The only parts replaced since were two connectors whose interface seals had hardened, not a crimp.

Certificates, compliance and four inspection gates

Certificate numbers, scope and expiry dates for ISO 9001, ISO 14001 and IATF 16949 go out with the quotation as PDFs, so your quality team can verify them against the issuing body rather than taking our word for it. The IATF scope and the audit history behind it are summarised in our IATF 16949 certification record, and the environmental side is documented under ISO 14001 / GB/T 24001. Environmental and material compliance is declared per shipment under RoHS 2011/65/EU as amended by 2015/863, with REACH SVHC statements and IMDS entries where your portal requires them. Where a program needs CE marking, it applies to the assembled diagnostic tool or test box, not to the passive harness, and we will say so plainly rather than print a logo that does not belong on the part. Wiring components are UL-recognized where the program specifies it, and the file number is on the drawing.

Inspection runs through four gates: incoming (wire, terminal, connector, seal, plating thickness by XRF, dimensional checks), in-process (first piece, crimp height every 500 pieces, pull test and cross-section per lot), end-of-line (100% continuity, pinout, four-wire resistance under load, insulation resistance, dielectric withstand), and outgoing AQL sampling with label and packaging verification.

Climate control, 5S and OEM customization

The terminal store runs at 20 ± 5 °C and below 60% RH under 5S and FIFO, not because a certificate demands it but because tin-plated terminals tarnish, and tarnish shows up as contact resistance drift eighteen months later rather than on the bench.

OEM customization covers logo, brand, length, color, AWG, connector mix, labeling and packaging. Connector bodies on our diagnostic lines are all-plastic or fully molded depending on the sealing class. A jacket compound change is a drawing revision too, and the thickness and flex trade-offs behind a UL 94 V-0 jacket on a diagnostic cable are the reason we ask which one you actually need. The same applies to a branded overmold or a non-standard cavity assignment: we will ask for a revision rather than absorb it silently into the build.

Most OEM wiring harness programs here are J1939 backbones and J1962 assemblies, and the six stages do not change between them. If your drawing happens to be the 16-pin side of the business rather than a 9-pin backbone, the standard part we build from is the J1962 16-pin OBD2 male adapter; the drawing review, the FAI and the PPAP package are identical.

FAQ

What PPAP level should a custom J1939 harness be submitted at?

Agree the level before the drawing is released, not after validation. Level 3 suits most OEM harness programs, with the full package submitted and samples retained at the supplier. Level 4 applies when the OEM defines additional requirements. Level 5 is for customers who want to review the package and the running process on site.

Can you build strictly to my drawing without changing it?

Yes, and we will tell you in writing what we expect to fail. We do not alter a customer drawing unilaterally. A real finding goes back as a question with the reasoning and the number attached. The decision stays with your engineering team, and the review record stays in the program file either way.

What do you need from us besides the drawing?

Node count, baud rate, routing environment and maximum ambient, mating connector part numbers, end-of-line test definition, PPAP level, annual volume and service life. Without the routing environment we can build the harness, but any validation we run would be a guess dressed up as a report.

How long does it take from drawing to signed PSW?

Twelve to eighteen weeks for a new design, six to eight for a variant on a validated platform. The program timeline in this article shows a real 17-week run, including two weeks lost waiting on connector samples. Programs that compress stage 4 tend to pay for it during the first year of production.

Do you supply terminators and shield grounding hardware?

Yes. 120 Ω terminators, backshell clamps, boots and cavity plugs can ship loose, pre-installed, or as a service kit, depending on whether the harness is installed on your line or by a technician in the field.

Which standards do your validation tests follow?

Your specification governs first. Where you do not specify, our defaults are ISO 16750-3 and -4 for vibration and thermal, ISO 9227 for salt spray, IEC 60529 and ISO 20653 for ingress, ISO 16750-5 for chemicals, and SAE/USCAR-21 for crimp validation. Subcontracted tests run at ISO/IEC 17025 accredited laboratories, and the scope certificate goes into the PPAP file.

Can you work from a sample instead of a drawing?

Yes, with a limit worth stating. We can reverse-engineer geometry and pinout from a sample. A sample cannot tell us the ambient temperature, the load, the node count or why the original failed. Building from a sample without that context produces a copy that inherits the original’s faults, which is usually what the customer was trying to escape.

How do you handle engineering changes after PPAP?

Every change goes through an ECN before build, and the PPAP package is reissued against the new drawing revision. A label change may need nothing more than a control plan update. A change to the terminal plating stack reopens salt spray and the PSW, because that stack is the reason the test passed.

Do you provide IMDS, RoHS and REACH declarations?

Yes. Material declarations are issued per shipment under RoHS 2011/65/EU as amended by 2015/863, with REACH SVHC statements. IMDS entries can be submitted by us or by the material supplier, depending on which portal your program uses.

What is the most common drawing error you see on J1939 harnesses?

The 9-pin Deutsch pinout drawn from the wrong view. Wire side and mating face are mirror images, and a drawing that does not state which one it uses will eventually be built backwards. The second most common is a shield terminated with a pigtail, which is electrically a different part from the one that was validated, even though it looks identical on the drawing.

Send the drawing, not the questionnaire

If you are starting a J1939 harness program, the most useful thing to send is the drawing, the connector list, and one paragraph about where the harness lives: ambient, routing, node count, and what happens if it fails.

What to send, and who reads it

That is enough for a real engineering review. You will get a written response on the electrical and mechanical risks, the wire schedule we would propose, and the validation we would run, before anyone discusses volume.

How to reach the engineering desk

Custom lengths, custom AWG, logo and brand, connector mix, test reports and PPAP Level 3 documentation are part of the normal workflow here. As a direct J1939 harness manufacturer, the review usually finds the problems before the engine does, which is the only reason to send a drawing to a factory rather than a catalog.

Get Your Custom Quote Instantly

Looking to expand your pet product lineup? Get a quick, customized quote from us. Discover how our communication cables solutions can boost your sales.

Let’s grow your business together!

Share

Friendly technical support representative

Hi, I’m the author of this post, and I have been in this field for more than 12 years. If you want to wholesale cables, feel free to ask me any question.